Change Managment

  • February 17, 2026
  • 1 reply
  • 20 views

RyanF56
Apprentice
Forum|alt.badge.img+1

How is everyone delivering all “Awaiting Approval” or “Pending Review” changes to their CAB Board?  I know it can be done manually by copy/paste each Change URL into an email and sent out, but was wondering if anyone has created a scheduled report or something similar.  I started to play around in Analytics by cloning the Change Overview report, but I’m unable to get the URL for each change into the report to allow for quick access to each change.

Thanks

1 reply

  • Apprentice
  • March 5, 2026

Hi Ryan,

Our CAB chair reviews all submitted changes each week and once ready for CAB assigns the CAB approvers to each change ready for Board and sets the status as awaiting approval. This then sends them a notification email for each change. However, they’re not reliant on that as we have a specific view within CAB which we’ve called CAB Agenda. All approvers within CAB have access to this view and it’s from here that we work through the changes to be discussed that day and progress them.

 

Kind Regards,

Karyn