FreshService uses several phases in the CM process.
Open
Planning
Waiting approval
Pending release
etc.
But I cannot figure out how to change these. I want Development, SIT, UAT, etc. Not the default ones. How do I add my own (custom) CM phases?
FreshService uses several phases in the CM process.
Open
Planning
Waiting approval
Pending release
etc.
But I cannot figure out how to change these. I want Development, SIT, UAT, etc. Not the default ones. How do I add my own (custom) CM phases?
Hi
In order to have more different phases, you will need to first create them under Status field in the ‘Change fields’ settings.
Admin → Field Manager → Change Fields
Post that, you will be able to define your workflow under the change Lifecycle settings.
Ref: https://support.freshservice.com/en/support/solutions/articles/236100-manage-your-change-processes-with-change-lifecycle
Thanks! So simple yet I struggled for an hour and could not figure it out. I was looking to add new phases under Change Lifecycle itself.