Hi,

I’d like to create a workflow which is triggered by the end date from the Pending Release.

I have the correct condition:

But I’m having trouble defining the Event.

Is it “Change is updated”?

icon

Best answer by eeha0120 4 April 2024, 20:46

View original

1 reply

Userlevel 6
Badge +11

Hi.

It seems you’re willing to create a workflow to run based on Dates, but are trying to create it as Event-based.

If your criteria is based on Dates, you should create a Scheduled workflow then:

 

Scheduled workflows run based on Dates with the frequency you set.

 

Hope this helps.

 